LTP3 Hinckley Area Project Phase Zone 4 - Proposed Transport Improvements.

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: No

Decision:

(a)       That the comments of the Environment and Transport Overview and Scrutiny Committee be noted;

 

(b)       That the outcome of the LLEP’s Growth Deal 3 bid to the Government’s Single Local Growth Fund submitted in July 2016 which did not secure funding for the Hinckley Area Project Zone 4, and the effect of this on the proposed package of works previously considered by the Cabinet in September 2016 be noted;

 

(c)        That the outcome of the stakeholder consultation on the prioritisation of schemes to be included within Zone 4 of the Hinckley Area Project in light of the significantly reduced funding available be noted;

 

(d)       That the revised list of schemes for Zone 4 of the Hinckley Area Project, detailed in Appendix D attached to the report, for implementation in 2017/18 using the remaining £800,000 of the LLEP’s 2014 successful Single Local Growth Fund bid, be approved.

 

(KEY DECISION)

 

REASON FOR DECISION:

 

In order for a revised number of Zone 4 works of the Hinckley Area Project to commence using the significantly reduced funding available as a result of the Council failing to secure funding through the LLEP Growth Deal 3 bid.

 

Divisions Affected: Burbage; De Montfort; Earl Shilton; Groby & Ratby; Hollycroft; Mallory; Market Bosworth; Markfield, Desford & Thornton; St Marys;

Publication date: 18/09/2017

Date of decision: 15/09/2017

Decided at meeting: 15/09/2017 - Cabinet