Minutes:
The Commission considered a report of the
Chief Executive and County Treasurer concerning the Revised Estimate for
2001/02 and the proposed revenue budget for 2002/03. A copy of the report marked ‘C’ is filed with these minutes.
The Commission also considered the
comments/decisions of the Health and Social Care, Education and Heritage. Planning and Environment and Finance
Scrutiny Committees in respect of the revised estimate and proposed revenue
budget. A copy of the supplementary
report, marked ‘CC’, (Annexes 1 – 5) is filed with these minutes.
The Commission also considered additional
information that had been provided and the request of Scrutiny Committees
(Annexe 6) and the following two letters that had recently been reviewed:-
(i) Letter from The Rt.Hon. Estelle Morris
MP – Secretary of State at the Department for Education and Skills concerning
the ‘passporting’ of education funding and the level of delegation to schools
(copy attached Annexe 7).
(ii) Letter from Mr. F. Straw – Leader of
North West Leicestershire District Council setting out that Council’s position
in respect of Concessionary Travel for disabled people (Copy attached Annexe
8).
Copies of these two letters and the
additional information requested by Scrutiny Committees are filed with these
minutes.
General
Matters
During the
discussion on the general issues relating to the budget the following points
were made:-
Final Revenue Support Grant (RSG)
Settlement
There had been some minor changes arising from the finalised RSG settlement,
the effect of which was an increase in the RSG received by the Council by
approximately £60,000. There would also be some other changes in funding and
expenditure since the proposed budget had been compiled.
Consultation on the Budget
In response to criticisms from some members regarding the contents of
the budget leaflet and the consultation process in relation to the budget
proposals, the Leader reminded members of the consultation process undertaken
when developing the Medium Term
Corporate Strategy. The development of the Medium Term Corporate Strategy,
including the consultation undertaken thereon, satisfied the requirements of
the Constitution to consult on a budget strategy, because it established the
priorities of the Administration and, therefore, of the budget process. The
Leader reminded the Commission of other consultations that had taken place,
particularly with schools and of the publicity in the local press.
The budget leaflet sought to provide
information in broad terms on how the County Council was funded, the pressures
on services due to increased cost and demands, the priorities in the Medium
Term Plan on which additional expenditure was being proposed and the impact of
these on the Council Tax. The Leader acknowledged the need to ensure that the
leaflet sent out with Council Tax bills should seek to explain the reasons for
the proposed increase in Council Tax as was always the case and the main reason
why such leaflets were produced.
Comments/Decisions
of Scrutiny Committees
During the discussion
on the comments made by Scrutiny Committees relating to the budget the
following new or additional points were made:-
Health and Social Care (Annexe 1)
Payments to Independent Sector
Providers
The proposed increase in payments to independent sector providers of
residential and nursing care at the different bands ranged from 4% to 5.3%. The
increased payments were being made to reflect the additional cost being
incurred by the care sector arising from the introduction of the minimum wage,
working time directive, labour market competition and increased operational
costs. The Commission was also reminded of the proposed new care standards for
residential and nursing care to be introduced shortly, which would have an
impact on the costs of care provision.
Direct Payments
The Commission noted an issue raised about the level of Direct Payments
to disabled people and their carers. The Commission was of the view that this might
be a matter for the Health and Social Care Scrutiny Committee to consider.
Education and Heritage (Annexe 2)
Snibston Discovery Park
The Commission was advised that a significant portion of the £167,000
growth in the Museums budget was to cover the shortfall in income at Snibston
Discovery Park. The two main areas of concern
regarding Snibston were the need to improve income and the need for substantial
capital investment. The Cabinet was planning to carry out a review of the
future of Snibston, which would seek to address relevant issues and consider
options for the future management of Snibston. The additional provision in the
budget was to ensure the continuing viability of Snibston, pending the review.
Leicester Theatre Trust
(Haymarket)
The Commission was advised that whilst a Service Level agreement had
been agreed with the Leicester Theatre Trust there was no commitment given to
on-going funding.
The Commission was advised that the Leicester Theatre Trust had recently
been awarded an additional grant of £450,000 from Central Government. Members
were also advised of the current proposals by Leicester City Council regarding
the development of a ‘cultural quarter’ in the City which could affect the
future location and possible operation of the Haymarket.
It was proposed that a Cultural Strategy would be prepared. That
Strategy would guide the development of theatre provision to communities in
Leicestershire and the use to be made of services provided by the Leicester
Theatre Trust would be reviewed at that stage.
Donington le Heath Manor House
Concern was expressed by some members about site security if the
proposals to close the establishment during weekdays were approved and about
the loss of a valuable educational facility.
The Leader advised that he had received representations from members of
the public about the proposals and indicated that he would draw these and the
comments made by Scrutiny to the attention of the Cabinet.
Planning and Environment (Annexe 4)
Environmental Management Scheme
The Commission was advised that the proposed implementation of this
reduction in the budget would mean that existing schemes would not be abandoned
but would be phased over a longer period of time.
The view was expressed by some members of the Commission that these
schemes provided an opportunity for the County Council to take the lead in
devising environmental improvement schemes with the possibility of some matched
funding. The Cabinet was therefore asked to consider a relaxation of the rules
governing the Shire Grants Scheme to enable the Planning and Transportation
Department to adopt a more proactive approach, should the provision for
Environmental Management Schemes be reduced.
Concessionary Travel
The Commission expressed its regret and concern at the decision of North
West Leicestershire District Council not to agree to changes in the scheme so
as to enable disabled people to take advantage of concessionary rate travel
before 9.30am. and was of the view that the
Cabinet should continue to seek agreement on this matter.
Combined Fire
Authority Budget
The Commission
noted that further discussions had now taken place with representatives of the
Combined Fire Authority (CFA). The Authority would be considering a revised
proposal at its meeting on 6th February and it was hoped that the
proposed CFA budget would be one that the Cabinet could commend to the County
Council.
Conclusion
It was moved by Mr.
Rhodes and seconded:
a) That the Cabinet be advised that the Commission supports the
proposed Revenue Budget for 2002/03;
b) That the views now expressed, together with the
comments/decisions of the four Scrutiny Committees be drawn to the attention of
the Cabinet and County Council
An amendment was moved by Mr. Wilson and seconded:
“That part (a) of the motion be amended to read as follows:-
‘(a) That the Cabinet be advised that the Commission notes the
proposed Revenue Budget for 2002/03.’ ”
The amendment was put and not carried, 7 members voting for the
amendment and 8 against.
The motion was put and carried, 8 members voting for the motion and 7
against.
RESOLVED:
a) That the Cabinet be advised that the Commission supports the
proposed Revenue Budget for 2002/03;
b) That the views now
expressed, together with the comments/decisions of the four Scrutiny Committees
be drawn to the attention of the Cabinet and County Council.
Supporting documents: