Minutes:
The Commission considered a report of the Director of
Corporate Resources, the purpose of which was to provide an update on the
2020/21 revenue budget and capital programme monitoring position as at the end
of period 10 (the end of January 2021). A copy of the report marked
‘Agenda Item 10’ is filed with these minutes.
Arising from discussion the following points arose:
(i)
Each government grant was subject to its own
conditions and many required the money to be spent within a set timeframe or at
the very least by the end of the financial year. This was very difficult
for many local authorities to achieve and therefore such conditions had been
softened to require spend to only be committed this financial year. This
meant some funds could now be carried forward to 2021/22. However,
despite this, the potential funding gap in 2021/22 remained substantial.
(ii)
Nationally, vacancy levels in care homes had
increased as views on preferred care settings continued to change towards care
at home. Some providers were beginning to close some homes which were no
longer viable, though this did not seem to be an issue in Leicestershire at the
current time. The County Council had provided interim support to
local care homes and they had adapted well during this difficult time. It
was accepted, however, that further pressures on the market lay ahead.
(iii)
Members noted the overspend on commercial
services, recognising that this had been a very difficult year for the
Council’s traded activities. Members were advised that services would be
reviewed on a case by case basis. Where a fundamental review was
necessary requiring significant changes to a service area, proposals would be
presented to the Cabinet and the Scrutiny Commission in the usual
way. Members noted that whilst some areas, such as cafes in parks,
had continued to do well, other areas had been significantly impacted by Covid
restrictions, for example, Beaumanor Hall which had been closed for almost a
year.
(iv)
The Cabinet would consider the reallocation of
unringfenced undersepnds as part of the usual outturn in May/June and redirect
such funds as it considered appropriate at that time.
(v)
The M1 Junction 23/A512 overspend would not
likely increase further as the scheme was due to be completed in May
2021. It was hoped that further funding received through section 106
developer contributions would reduce the overall cost to the Council.
(vi)
A member questioned what would happen to the
section 106 funding secured for the creation of secondary places in the
Coalville area now that this could not be used towards a new building at
Newbridge High School. The Director advised that this would depend on the
specific terms of the section 106 agreement entered into with the
developer. The Head of Law confirmed that the agreement would be reviewed
to ensure, as far as possible, the funding was not lost but reallocated as
appropriate.
(vii)
A member asked for an update on the proposed
development of Leaders Farm in Lutterworth which had been progressing for some
time. The Director confirmed this was not yet developed enough to be
regarded as a live scheme within the capital programme. Work to secure
planning permission for the site was still in progress.
(viii)
A member raised concern about the continued
slippage and increased costs for the proposed Zouch Bridge replacement which
had been ongoing since 2013. Members noted that refurbishment techniques
had improved over recent years and consideration would therefore be over the
summer to whether this would be a viable option, as opposed to its
replacement. A further update would be provided as part of the MTFS monitoring
report in the Autumn. The Director confirmed that the bridge continued to
be subject to regular inspections and that works to date had ensured that it
had remained open. Whilst it was noted that the River Soar was the
boundary between Leicestershire and Nottinghamshire, the bridge fell within
Leicestershire County Council’s remit.
(ix)
Members raised concerns about the length of time
some schemes remained listed in the capital programme and questioned how these
were reviewed to ensure extensions or other changes did not affect the best
value assessments or forecasted yield/returns estimated when they were first
agreed, particularly when some were listed for several years. A member
raised further concerns about schemes not listed in the programme but which
were under development (such as Leaders Farm) and which still incurred costs in
the background. Members questioned how long a scheme was or should
continue to be pursued, the cost implications of this and what was the overall
impact on the capital programme.
The Director
emphasised that schemes tended to be added to the capital programme long before
construction works began. This was felt to be appropriate to allow for
proper oversight and management of the programme over the duration of the MTFS
(i.e. 4 years). However, it was acknowledged that timescales were
sometimes overoptimistic, and this was something officers were seeking to
address.
The Director confirmed that the continued extension of schemes could
result in increased costs and use of officer time. Members noted
that business cases for a project would be assessed at the outset and
thereafter reviewed as necessary following any change, but a review of the
overall capital programme for the overall impact of delays was not carried out.
The Director agreed
to consider the concerns now raised both in respect of individual schemes and
the programme overall. He further agreed to consider the need for
stricter timelines for both schemes listed in the capital programme and those
which were under development. Members requested that the next MTFS
monitoring report presented to the Commission provide some narrative on these
issues and detail projects which had been delayed, the justification for this
and potential cost implications.
RESOLVED:
(a) That the update now provided
be noted;
(b) That the Director of
Corporate Resources be requested to consider the concerns now raised by the
Commission and to provide an update in the next MTFS Monitoring report to the
Commission in the Autumn.
Supporting documents: