Minutes:
The Commission considered a report of the Director of Corporate Resources which set out the provisional revenue and capital outturn for 2022/23. A copy of the report marked ‘Agenda item 11’ is filed with these minutes.
The Chairman welcomed Mr L. Breckon CC, Lead Member for Resources, who attended for this item.
Arising from discussion, the following points arose:
(i)
A Member raised concerns that whilst the meeting
held between the Leader, Deputy Leader, Lead Member for Resources, Chief
Executive, Director of Corporate Resources and the Chancellor, Jeremy Hunt MP,
had been promoted to be a success, it was not clear what tangible outcomes had
been achieved. The Lead Member for
Resources confirmed that the discussions had been helpful and promising, but
that there would not be an overnight fix.
Officers would next be meeting with Government officials to discuss the
Council’s proposed solution in more detail.
(ii)
As the Government did not propose to look at
Fair Funding for local government until 2025/26, the Council was seeking the
early introduction of a funding floor (which was part of the overall solution
for Fair Funding) as soon as possible.
This had been done for schools and so was technically possible, but it
was not yet clear if this would be practicable given national financial
pressures. It could, however, make a
significant difference to the Council’s immediate financial position.
(iii)
Whilst many tourist attractions were bouncing
back after the Pandemic, a Member commented that Beaumanor Hall still appeared
to be lagging behind and questioned if the Council had the right skill set to
perhaps diversify and maximise trading opportunities at this site. Members noted that advisers had been
consulted on how best to drive this part of the Council’s traded service
forward, particularly in respect of weddings.
(iv)
Whilst Members were pleased to see business
rates were being retained locally, concerns were raised about ongoing discussions
as to how this would be split between the City, County and district
councils. Members noted proposals for
the income to be split by way of a third each, but that much of the growth
coming into Leicester and Leicestershire would fall within the County and so
would likely affect the County Council more than the City Council. The Lead Member commented that it was right
for the Council to seek to ensure it received a fair split that would reflect
where growth would fall. However,
Members raised concerns that if an agreement could not be reached, there was a
risk that the income would revert back to Government resulting in significant
loss to all, although it would be in no local council’s interest if this did
happen. Members encouraged continued
dialogue between the respective Council Leaders and for a resolution to be
found as soon as possible.
(v)
Post the Covid-19 pandemic it was clear that
more resources were needed in adult social care services. The Department had done a lot of innovative
work over the last four years to reduce costs but not the quality of service
and that it had performed well despite the challenges faced during that
period. However, a Member commented that
more needed to done by the NHS locally as Leicestershire had the fewest number
of nursing places funded within the community.
A Member commented that this was a key issue that needed to be
addressed.
(vi)
Members raised concerns about the continued
level of slippage within the capital programme and the impact this had on
overall costs incurred. A Member
commented that large schemes cost a lot in officer time which also increased
with delay. The Director commented that
slippage would always be incurred, and in part was due to the single cut-off
date at the end of the financial year.
Slippage was also more likely in time of high inflation as investments
needed to be regularly reassessed in light of the latest information
available. Members noted that the
quarterly budget monitoring reports presented to the Commission identified
where slippage would likely be incurred to keep Members informed throughout the
year.
(vii)
A member questioned the likely impact of
slippage on the provision of additional school places and the SEND Programme.
The Director commented that ultimately most of the slipped scheme would be
delivered eventually. Whilst there would
inevitably be some impact on delivery of required school places, much of the
slippage was due to revised timelines for developer funded housing development.
(viii)
The costs of repairing Zouch bridge continued to
rise and delays in being able to secure government funding for the project had
been an issue as the Council’s initial levelling up bid had been
unsuccessful. Options were being
considered.
(ix)
Consideration was being given to all options to
pursue the Lutterworth East SDA now that the judicial review case had been
resolved. Members noted that the scheme
would need to be reviewed as much had changed since this had first been put
together both in terms of cost estimates, and in terms of the need for office
space post Covid. This was being worked
on by officers and an update would be provided in due course. Members requested that a detailed update on all
Investing in Leicestershire Programme projects be provided as part of the
planned annual performance report on the Programme which it was due to receive
in September.
(x)
A Member questioned the reasons for delay in the
Council, as the Highway Authority, being able to agree road schemes which were
developer led. Delays resulted in costs
increasing over time which in turn risked developers choosing to no longer
build on the basis these schemes became unviable. A member commented that this posed a risk to
residents that needed this infrastructure, and to the County Council that might
then have to provide alternative highway solutions. It was questioned to what extent delays were
balanced against these kinds of risks.
It was suggested that this should be the subject of a separate report to
the Highway and Transport Overview and Scrutiny Committee.
(xi) A Member sought more clarity on the current position regarding delivery of the Melton Mowbray Distributor Road (MMDR). It was noted that whilst the North and Eastern section of the road had been approved and funding secured, the southern section was currently in the design and testing stage. It was suggested that a briefing for relevant local members be provided regarding current progress.
RESOLVED:
(a) That
the provisional Revenue and Capital Outturn for 2022/23 be noted;
(b) That
a detailed update on all Investing in Leicestershire Programme projects be
provided as part of the planned annual performance report on the Programme which
it was due to consider in September.
(c)
That a report be presented to a future meeting
of the Highway and Transport Overview and Scrutiny Committee regarding the
process and balance of risk undertaken by the Council as the highway Authority
in respect of developer led road schemes.
(d) That relevant local Members be updated regarding current progress on delivery of the MMDR.
Supporting documents: