Minutes:
The Committee
considered a report of the Director of Environment and Transport, the purpose of
which was to inform the Committee of the development of the Environment and
Transport Department 2024/25 Highways and Transportation Capital Programme and
Works Programme, both of which were appended to the report, and to seek its
view prior to these Programmes being presented to the Cabinet for approval on
26 March 2024. A copy of the report
marked ‘Agenda Item 8’ is filed with these minutes.
Arising from
discussion, the following points were made:
(i)
Members
welcomed the recent announcement of Network North Funding (NNF) allocated by
the Government. An indicative
allocation for the County Council of £238m under the Local Transport Fund (LTF)
element of NNF had been announced which would be received over a period of 7
years beginning in 2025/26. Members
noted that this did not therefore form part of the current capital programme
now presented for comment.
(ii)
The
annual allocation of the LTF had not yet been confirmed. The Department of Transport (DfT) had
indicated that this would be back loaded (i.e. start low and increase year on
year). The Director suggested it would
therefore be a while before substantial funding was received. Full details were awaited, but indications
were that the funding could be spent on a wide range of capital works. Further guidance was expected by the end of
March.
(iii)
In
response to questions about how the back loading of funding might affect
activity in the earlier years, the Director explained that larger projects had
a long lead in time due to the level of preparation and planning needed. It would therefore be possible to plan these
scheme and contract at appropriate times in line with when funding would be
received. This would also become clearer
when the annual allocations had been confirmed.
(iv)
Low,
static levels of funding in recent years had limited the amount of improvement
and maintenance works carried out by the Department. Members were pleased to hear that the NNF
would allow for a more long-term approach to be taken. The Director highlighted, however, that some
context was required to manage expectations. The Department’s current capital
budget for maintenance was £18m for 2024/25, and the additional NNF Road
Resurfacing funding stream for maintenance would increase this next year by
approximately £2.25m. Whilst the funding
would be welcome, it would not therefore address all the issues currently faced
across the County’s road network.
(v)
The
Department was required to develop a two year delivery plan for the LTF by the
end of the year. Officers were currently
working on this and engagement with members, MPs and other stakeholders would
take place as appropriate over the coming year.
The guidance expected later this month would provide more clarity on
what could be included in the plan.
(vi)
Members
welcomed the announcement by Government of a LTF for highways and transport
capital improvements. This would be
aimed to support more small-scale improvements across the network. The Director reported that if this came to
fruition, along with the Road Resurfacing NNF, an improved capital program
might be possible in future years.
(vii)
Funding
would, if appropriate under the conditions of funding and where investigations
highlighted possible schemes, be set aside to support flood alleviation
work. A significant amount of work had
been undertaken in response to recent storms, like Storm Henk. However, this was in addition to considerable
work still in progress from ongoing section 19 investigations which related to
past flooding events. Investigations
took time to resolve and would likely result in actions for the various flood
risk management authorities including the County Council in its role as Highway
Authority. Some funding would therefore
be allocated to deliver these.
(viii)
A
Member questioned if funding would be targeted to more hard-wearing,
longer-term repairs, noting that a lack of resources had meant more short-term
fixes to the road network in recent years.
There were concerns that over time this had affected the overall
standard of the network which now needed to be addressed. The Director confirmed that this would be the
planned approach and a holistic view of assets (highway, drainage and street
lighting) would be taken.
(ix)
Members
commented on the deterioration of pavements and the need for some of the new
funding to be targeted towards addressing this in future years, as well as
roads. It was acknowledged that a lack
of resources had meant that minimal maintenance works to pavements and
cycleways had been possible for some time. The NNF would help address this.
(x)
A Member
questioned how the Department sought to ensure adequate section 106 developer
contributions were secured from logistics developments given these would have a
greater, long-term impact on roads due to HGVs travelling to and from such
sites. It was noted that the Highway
Authority sought to include conditions that monitored the impact of the
construction phase on the highway.
However, there was no mechanism for the Council to seek contributions
for future general maintenance which had to be managed by the Council as
business as usual within its normal maintenance budget. Members noted that to seek more through the
section 106 process would require a change in national policy.
(xi)
Members
were pleased to hear that the Department was undertaking a review of its
approach to pedestrian crossing requests.
The conclusions of this review would be shared with Members as
appropriate.
The Lead Member for
Highways and Transport commented that the additional NNF and potential LTF was
to be welcomed. This would be targeted to address local highways issues, which
would include pavements and cycleways.
There was some risk, however, regarding future years as a change in
Government might result in changes being made to the fund and/or the levels of
allocation.
RESOLVED:
(a) That the development of the
Environment and Transport Department 2024/25 Highways and Transportation
Capital Programme and Works Programme be noted;
(b) That the comments now made be
presented to the Cabinet at its meeting on 26 March 2024 for consideration.
Supporting documents: