Issue - decisions

Newhurst Quarry - Energy Recovery Facility

22/05/2020 - 2020/0072/02/ (2019/VOCEIA/0292/LCC - Biffa - To accommodate proposed changes to the design of the plant including materials used in the construction and the external appearance of the plant; the removal of the IBA maturation area and relocation of t

(a)        That the application be permitted subject to the conditions nos. 1-31 as set out in the appendix to the report;

 

(b)        That the Board confirms (as required by the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended) that in dealing with the application the County Council worked in a positive and proactive manner, taking account of paragraph 38 of the National Planning Policy Framework.